Economy - 20 June 2026
Uganda Nears First Oil as Cabinet Inspects Kingfisher Project in Kikuube
KIKUUBE, June 22, 2026 - Uganda's preparations for first oil received a major boost as the Vice President and the Prime Minister led a Cabinet delegation to inspect progress at the Kingfisher Oil Development Project, where construction has entered its final stages.
The visit highlighted significant progress at the project, with construction of the Central Processing Facility reported to be 99 percent complete and commissioning activities reaching 74 percent. Of the 31 planned production wells, 22 are ready for production, bringing the project closer to commercial oil production.
Project officials said the Kingfisher development, together with the Tilenga Project and the East African Crude Oil Pipeline (EACOP), has attracted investments exceeding US$12 billion, making the integrated oil developments among the largest industrial investments in Uganda's history.
The Cabinet delegation was also briefed on preparations for the safe commissioning of the facilities and the remaining activities required before first oil is achieved.
Government representatives reaffirmed their commitment to providing a stable investment environment and the infrastructure needed to support Uganda's emerging petroleum industry, emphasizing that the sector is expected to drive industrialization, economic growth, and long-term energy security.
The delegation also reviewed ongoing national content and community development initiatives associated with the project. Thousands of Ugandans have participated in project activities, while investments in education, healthcare, agriculture, skills development, and access to clean water have been implemented in host communities.
Project developers reiterated their commitment to achieving first oil safely and efficiently while ensuring the development delivers lasting economic and social benefits for Uganda.
Related reading

Economy - 31 August 2026
Rwanda Reclaims Undeveloped Industrial Plots To Improve Land Use
Kigali, August 31, 2026 - Rwanda reclaimed 15 additional industrial plots from investors that failed to develop them within agreed timelines, reinforcing the government's push to ensure scarce industrial land is put to…
By Jean-Marc Okito - 2 min read

Economy - 31 August 2026
High Costs And Information Gaps Slow Solar Uptake Among Farmers
Kampala, August 31, 2026 - High upfront costs and limited information are holding back adoption of solar technologies among Uganda's smallholder farmers, constraining productivity and post-harvest management.
By Jean-Marc Okito - 3 min read

Economy - 31 August 2026
Parliament Cafeteria Closure Exposes Procurement Dispute Over Shs2 Billion Food Deal
Kampala, August 31, 2026 - A procurement dispute over a Parliament catering contract worth between Shs1.3 billion and Shs2 billion has disrupted cafeteria services for lawmakers and staff.
By Jean-Marc Okito - 2 min read